Arthur Astarita, Maine State Lead, RCAP Solutions, Inc
RCAP Solutions’ experience has shown that small-sized systems (<3300 connections), have a wide-range of ways to document the need for capital improvements. Typically, the superintendent has a list showing improvements including costs that is used to plan proposed upgrades. This “mental list” is generated and updated when events arise but does not contain a comprehensive look at the entire system and its’ financial health. It is not holistic view which is required to assure the system is operated in a long term and responsible manner. Conducting a collaborative infrastructure assessment through an asset management planning process produces a thorough document that can be utilized by the utility* and shared with the town or even regional economic development groups.
RCAP Solutions has been conducting asset management processes with five water utilities in Oxford County Maine (Figure 1). These water utilities are relatively close geographically; the largest towns of Mexico and Rumford are separated by a bridge over the Androscoggin River. The five towns are part of the nine-town River Valley Region of the Western Maine Economic Development Council (WMEDC-RVR). The River Valley Region has a population of about 13,250. “Public” water is delivered to about 12,000 people or 90% of the WMEDC-RVR population. The drinking water for the residents of the four remaining towns is sourced by private wells.
The hub of this region is Rumford, the largest community and home to the largest employer, Canadian based Catalyst Corporation’s Wood Mill. At the end of 2014, the mill employed 800 workers; within 5 months they laid off 50 people. The mill is the critical economic lifeblood of the area. The Rumford Water District* realizes about 30% of their revenue from the mill whereas the surrounding water utilities have many indirect benefits. A study by the Maine State Office of Policy and Management (OPM) of population trends between 2010 and 2030 predict a population decline of 33% WMEDC-RVR (http://maine.gov/economist/projections/index.shtml). Such estimates should weigh heavily on the regions’ towns and possible coping mechanisms should be activity discussed.

Figure 1: Oxford County Water Infrastructure Asset Management Project showing the five core towns and the four other towns comprising the River Valley Region of the Western Maine Economic Development Council.
RCAP Solutions’ project work for Andover and Canton Water Districts included creating a digital map of each system; the other three systems (Dixfield, Mexico, Rumford) already had digital maps. The tables from digital map layers provided a raw inventory for critical water equipment such as hydrants, valves, distribution pipe, source, treatment and storage. Individually, each system carried that inventory into a spreadsheet containing questions including name, location, condition, installation date, life expectancy, criticality of failure and replacement cost. Each utility completed an asset management plan (AMP) using EPA’s CUPSS software. A quick view of each utility is shown in Table 1.

Table 1: Quick View of Utilities in this study (More details can be seen in the respective utility’s asset management plans-not included. State of Maine MHI is $48,453
Historically, most of the water utilities’ asset replacements, specifically valves and pipes, are driven by the State Department of Transportation and/or towns’ public works schedules. If roads, culverts, sidewalks or bridges are on State or Town schedules for repaving, the water utilities are then consulted. This silo scheduling creates interruptions with the water sectors’ normal replacement plans; it can also lead to replacing assets that have not reached their full useful life expectancy; payment for such pre-spending is the responsibility utility customers or town residents*.
Using the asset management process, the utilities can generate a repair/replacement (R&R) cost schedule. Here, items can be grouped by decade or by logical project task(s). This information is perhaps the most important and critical step in reaching effective utility management. This report initializes priority and emphasis on improvement types along with the cost of those upgrades or maintenance activities. The R&R cost schedule is critical, concise and organized. The information can be shared with decision makers overseeing the system, town, region and state. This sharing leads to enhancements to planning infrastructure improvements. Such cooperation will improve cooperation between utilities, towns and state along with sharpening the budget process for everyone.
As Table 1 shows, the median household income (MHI) of the project towns are below the state MHI, thus they qualify for grant assistance from increasingly competitive (and dwindling) federal and state programs. Historically, each water utility hires an engineering firm to scope the necessary capital improvements. Individually, they submit funding applications and separately bid-out construction. Consequently, they compete and are “ranked” against each other at two very important projects stages: funding and construction. In this project example, the collective utilities total distribution pipe is 76 miles. The amount of pipe, which generally relates to the amount of total assets, pales when compared to large and very large water systems. Accordingly, if these small, geographically close utilities are treated as “one system”, economies of scale are visible. Hiring one engineering firm for design and one construction company enhanced by bulk purchases of similar pipe, hydrants, valves, etc. could create cost savings on total collaboration-wide project.
To demonstrate an example process of collaboration between these five water systems, RCAP Solutions pooled each system’s asset management information into one CUPSS project. The combined analysis shows 2200 assets worth $76.8M; 727 assets are at high risk. The CUPSS software produces a capital improvement schedule which can be exported for spreadsheet analysis. A twenty-year improvement plan in five year increments can be presented. Figure 2 shows the collective twenty-year CIP for the five utilities. These twenty-year expenses represent only 18% of the total collective replacement value. The first ten years of capital costs by utility are shown in Figures, 3 and 4.

Figure 2: Oxford County Collaborative CIP Study – 20 Year CIP 2014-2034- 18% of the Total Collaborative Value
Granted each system has different scales of improvement costs. Some utilities need to review asset attributes in order to “smooth out” the overly large cost requirements in certain 5-year periods. However, costs to the collaborative are transparency and can be preserved by prorating costs along with factoring the capital expense with each utility’s revenue contribution to the collective.

Figure 3: Oxford County Collaborative CIP Study – 1st Five Years 2014-2019- 8% of the Total Collaborative Value

Figure 4: Oxford County Collaborative CIP Study – 2nd Five Years 2020-2024- <1% of Total Collaborative Value
A financial analysis of all five water utilities shows that perhaps jointly, they could accomplish the needed capital improvements. The revenue expenses are shown in the following graphics and tables indicates that for the two year period of 2012 and 2013 there was a collective $1.7M surplus.
After individually funding the necessary utility reserves: emergency (~25% of operation expenses), debt service along with replacement of short-term assets (asset with <15 year life expectancy), a portion of a utility’s surplus could be collective pooled for capital improvements to create an economy of scale. Of course, what certain projects are good of collaboration versus unique upgrades specific to an particular utility must be crafted.
This collaboration aids the water utilities’ sustainability and helps the economic development of the River Valley Region. Improved infrastructure attracts businesses. Using the existing framework of the WMEDC-RVR can help streamline planning amongst utilities, towns and regional groups. Given the OPM’s declining population projections and one pivotal declining employer in the RVR, it is RCAP’s opinion that the utilities and towns needs to 1) prepare for a lower revenue stream, 2) prudently accomplish as much infrastructure repair/replacement as possible, 3) collaborate in purchases and conducting infrastructure projects and 4) consider consolidating administrative operations.
As governmental subsidies decline, it is increasingly becoming apparent that small rural utilities must develop a holistic business plan which focusses on asset management in order to operate the system in a sustainable manner. It is the long-term asset reserve that is financially critical and challenging. However, it seems that individually, no one system can save reserves to significantly “buy down debt” of these expensive capital improvements while keeping customer rates reasonable. If major employers decline, a ripple effect occurs to the revenue available; expenses increase for the ever declining population base. Collectively working together could be a solution.